1) Tailings Storage Facility Stages 2 and 3 , Design and construction supervision , (October 2018 - Date) (Hummingbird Resources, Yanfolila Gold Mine , Mali)
2) New mine, All Earthworks and Civils, Primary accurate and precise Survey Control networks establishment, New Mine camp, Quarry, Export Facility (Conveyors, ROM Tip, 22.8 km Haul road . (January 2017 – August 2018) Bel air Bauxite Mine , Guinea
3) Contract Coal Mining and Associated Infrastructure, ( August 2014- December 2016) , Hwange Colliery, Zimbabwe
4) New Mine development, Haul Roads, Internal roads, sewer lines, sewer treatment plant and water line( July 2013 - July 2014) , Swakop Uranium Mine, Namibia
5) Construction of a sulphuric acid processing plant and gas cleaning processing plant , Tsumeb, Dundee Precious Metals , Namibia, 2013

offer img

Other Projects

1)Upgrading of Isoka-Muyombe-Chama-Lundazi road to Bituminous Standards in Eastern Province of Zambia-Lot 4: Chama (Muyombe road Junction)-Lundazi-84km , (June2016 – Date), Zambia
2)The Construction of Matumbo bridge and Kambemba bridge across Luangwa and Kambemba rivers in Chama District of Muchinga Province , (June2016 – Date) , Zambia ( Feb – May 2016) 3) Upgrading of Isoka-Muyombe-Chama-Lundazi road to Bituminous Standards in Eastern Province of Zambia-Lot Junction D145 and Lusuntha to 40km along Chama Lundazi road and From Lusuntha –Lundazi Chama Road Junction to Lusuntha Boarder Post (16Km) totalling-56km, Zambia (Feb – May 2016)
4)Upgrading to bituminous standards and re-alignment of approximately 91km of The Luangwa bridge to Luangwa Feira (D145) road in the Lusaka Province (Feb – Nov 2015), Zambia
5)Detailed Engineering Design for upgrading Of 259 km Of Luwingu to Kaputa Road. Nkhoshya-Kaputa road (D37) (101km)-Lot3(Feb – Nov 2015), Zambia
Botswana Projects: NOV 2010 – 2014
6) North South Carrier Phase2 –approximately 350km stretch _ MIN OF MINERALS, ENERGY AND WATER RESOURCES BOTSWANA
7)Rasesa Railway Spur-30km stretch _ Min of Transport and Communication, Botswana
8)Masama Wellfield Project Thamaga Infrastructure Development Phase 1 –(50km of bituminous township roads, storm water drainages and a Foot bridge) , Botswana, 2008